Earthship Academy - Session 2: Update (Day 18)

Update (Day 18) - Lemuria Global Model day 2 of a 3 day run this week. I personally was dealing with some illness and fatigue so I was unable to attend this day, but work continued in these areas:

  • Concrete foundation pouring
  • Metal flashing for greenhouse windows
  • Carpentry of ceiling 1x8’s cut and placed
  • Interior bottle wall construction for entry doors
  • Bathroom steps up to toilet and shower (cans/concrete)
  • Backfill dirt up to roofline