Earthship Academy - Session 2: Update (Day 22)

Academy (Day 22) - Lemuria Global Model day 2 of 2.. Basics of work performed today:

  • Grey water pump moved to above the interior botanical cell to catch any issues of water so that is falls into the cell.
  • Final coat of adobe applied to interior rooms
  • Kitchen cabinet boxes set in place
  • Interior door hardware attached
  • Roof and gutter dirt cleaned off to prevent dirt entering the cistern
  • Interior ceiling carpentry continued 
  • Vent box re-bar arches placed exterior

End of day Ron S. conducted a full tour of the building to go over the work we completed and what will be continued by Academy session 3.